PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)

                                 The Government of India launched the Pradhan Mantri Gram SadakYojan (PMGSY) on 25th December 2000.   PMGSY is a 100 percent Centrally Sponsored Scheme and 50 percent of the cess levied on High Speed Diesel (HSD) has been earmarked to fund the scheme. The primary objective of the PMGSY is to provide connectivity by way of an all weather road to the eligible un-connected habitations in the rural area, in such a way that all un-connected habitations with a population  of 500 persons and above are to be covered in plain area. In respect of Hill State (North-East, Sikkim, Himachal Pradesh, Jammu & Kashmir, Uttranchal) and the desert areas (as identified in the Desert Development Programme) as well as the    Tribal (Schedule-V) area, the objective would be to connect habitations with a population of 250 persons and above.

                                 The PMGSY will permit the upgradation (to the prescribed standards) of the existing roads in those districts where all the eligible habitations of the designated population size have been provided all weather road connectivity. However, it must be noted that upgradation is not central to the programme and can not exceed 20% of the state’s allocation as long as eligible un connected habitations in the state still exist.

 

       Procurement & Contract Management Manual for PMGSY RRP-II

       Bid Evaluation Report for Works Under RRP-II

       DPR Template for Preparation of DPRs under RRP-II

       Approved Bidding Document for Stage I (New Connectivity) under RRP-II

       Approved Bidding Document (Stage II) under PMGSY for RRP-II

         {Method of Preparation Click Here}

       Procedure For Preparation of ESMF DPR under RRP-II Project

      Project Preparation for the second World Bank Loan (RRP-II) Public Notice       

 Environment and Social Nodal Officer

Name

Mobile

e-mail

Address

Er. D.K Nag

98160-31424

d.knag@rocketmail.com

E-in-C Office, HP.PWD, Nirman Bhawan, Nigam Vihar Shimla-2 (H.P)

          World Bank
         Environment and Social Management Framework
         Environmental Codes of Practice
         ESMF & ECOP for RRP-II Projects
                    Public Disclosure
                    ESMF Study Report - Volume I
                    Social Management Framework - Volume II
                    Environmental Code of Practice (ECoP)

           Proposed PMGSY Rural Roads Project
                
    Public Disclosure
                 
    Executive Summary
                     Vulnerability Framework
                     Institutional Arrangements
                     Social Management Framework RRPII
                     Environmental and Social Management Framework
                    
Environmental Code of Practice


 

 

 

 

PHASE-WISE LENGTH OF ROADS CONSTRUCTED, EXPENDITURE INCURRED AND HABITATIONS CONNECTED UNDER PMGSY  AND WORLD BANK   (UPTO 30.11.2011)

Sr  No

       Phase          

No. of roads sanctioned

No. of completed roads

Sanctioned Amt.      (Rs. Crore)

Expt. upto 11/200   (Rs. Crore)

Length of proposed road (Kms.)

Length of roads constd. (Kms.)

No. of Habitations to be benefited

No. of Habitations  benefited

1

Phase-1    (2000-01)

127

127

60.00

59.77

534.600

534.600

302

302

2

Phase-II    (2001-02)

245

244

128.93

118.20

932.706

931.706

445

444

3

Phase-III   (2003-04

370

341

254.01

221.39

1881.935

1776.620

790

734

4

Phase-IV  (2004-05)

105

81

138.30

114.66

620.213

538.528

284

245

5

Phase-V   (2005-06)

105

80

141.27

102.42

614.496

519.586

297

262

6

Phase-VI  (2006-07)

391

250

530.06

370.89

2088.756

1663.889

833

572

7

Phase-VII (2007-08)

74

14

156.16

28.04

517.315

160.295

154

21

8

Phase-Vlll (2008-09) Bharat Niram & Panchayat Connectivity

13 1 34.23 6.43 96.290 20.885 29 1
9

Phase-IX(2009-10)Bharat Niram & Panchayat Connectivity

190 6 231.95 29.57 608.825 165.450 288 8

10

World Bank Phase-I     (2004-05)

115

106

89.98

81.65

587.640

570.215

264

250

11

World Bank Phase-II    (2005-06)

66

49

117.38

78.07

424.725

366.400

164

136

12

World   Bank  Phase -III  (2007-08

13

9

22.83

12.77

65.095

33.915

19

16

13

R.R.P-II (New Connectivity) 

15

0

30.22

0.00

66.565

0.00

32

0

Total

1829

1308

1935.32

1223.86

9039.161

7282.089

3901

2991

 Up-gradation under Bharat Nirman                                                 

 

1

Phase-VI(2006-07) Additional proposals

178

144

320.37

261.33

2042.160

1722.760

 -

 -

2

Phase-VII(2007-08)

47

29

111.75

61.99

619.735

379.435

-

-

3

Up-gradation Phase- VIII (2008-09)

6

2

14.47

5.06

48.855

13.680

-

-

4

Up-gradation Phase- IX (2009-10)

4 2 12.02 3.01 31.040 9.085 - -
5 World Bank Phase-III (2007-08) 31 14 75.63 39.42 362.82 191.352    
6 R.R.P-II (New Connectivity)Stage-II 97 0 125.99 0.00 545.597 0.000 - -

 Total

363

191

660.23

370.81

3650.207

2316.312

- -

 Grand Total

2192

1499

2595.55

1594.67

12689.368

9598.401

3901

2991

      For further details and tenders click on the following link :-

      http://pmgsytendershp.gov.in/nicgep/app      http://www.omms.nic.in      http://www.pmgsy.nic.in

                